Case Study - NIMBUS CIT

NIMBUS – CIT – BOSCO BATTERY TESTING AND TRIALLING - Cork (Commercial)

PV Generation worked closely with CIT and Nimbus to design and install a state-of-the-art battery and advanced control system testing and centre. We worked very closely with the CIT Health and Safety team to ensure all H&S risks were identified during the design phase and carried out close monitoring of the system during construction and commissioning. We then helped CIT develop the management and operating manuals. All modifications were carried out by PV Generation.

 

INSTALLATION DATA

BOSCO – CIT

 

Size of installation

8kWp

 

Purpose, system type

Battery Trialing, container mounted

 

Battery Type

10kWh – Aquion and 10kWh BYD Lithium Ion

 

Inverter

2 inverters – Aurora and Studer Innotec

 

Specials

Fully programmable load bank to simulate real domestic usage

 

Commissioned

June 2018